๐Ÿ“Š Bustan Energy โ€” Planning vs Execution

Project tracker for Beamtech Residences ยท BE-2026-001

Beamtech Block & Beam โ€” 32.5 kWp
Ref: BE-2026-001 Start: TBD Target: 8 weeks Status: Pre-sales
Overall Progress
32.5
kWp System
เธฟ1,056,250
EPC Budget
56
Panels
0 / 8
Weeks Done
เธฟ0
Spent So Far
Phase Task Planned Start Planned End Actual Start Actual End Delta Status Owner
1. Pre-Sales Receive construction plans 9 Mar 9 Mar 9 Mar 9 Mar โœ“ Done Kaniel
System design & sizing (32.5 kWp) 9 Mar 9 Mar 9 Mar 9 Mar โœ“ Done G (AI)
Proposal created (EN/HE/TH) 9 Mar 9 Mar 9 Mar 9 Mar โœ“ Done Noa (AI)
Send RFQ to 5 suppliers 10 Mar 10 Mar โ€” โ€” Planned Kaniel
Receive supplier quotes 10 Mar 17 Mar โ€” โ€” Planned Kaniel
2. Sales Present proposal to Beamtech Week 1 Week 1 โ€” โ€” Planned Kaniel
Client selects option (A/B/C) Week 1-2 Week 2 โ€” โ€” Planned Client
Contract signed + deposit received Week 2 Week 2 โ€” โ€” Planned Kaniel
3. Engineering Site survey + roof measurement Week 2 Week 2 โ€” โ€” Planned Engineer
Structural approval (Rock Engineering) Week 2 Week 3 โ€” โ€” Planned Rock Eng.
PEA license application Week 3 Week 5 โ€” โ€” Planned Kaniel
4. Procurement Place equipment order Week 2 Week 2 โ€” โ€” Planned Kaniel
Delivery to Surat Thani Week 3 Week 4 โ€” โ€” Planned Supplier
Ferry to Koh Phangan + site delivery Week 4 Week 4 โ€” โ€” Planned TM Dev
5. Installation Building 1 โ€” mounting + panels Week 5 Week 5 โ€” โ€” Planned TM Dev
Building 1 โ€” inverter + wiring Week 5 Week 5 โ€” โ€” Planned Electrician
Building 2 โ€” mounting + panels + wiring Week 6 Week 6 โ€” โ€” Planned TM Dev
Battery installation (if Option C) Week 6 Week 6 โ€” โ€” Planned Electrician
6. Commissioning System testing & QA Week 7 Week 7 โ€” โ€” Planned Engineer
PEA inspection + meter install Week 7 Week 8 โ€” โ€” Planned PEA
Handover + monitoring setup Week 8 Week 8 โ€” โ€” Planned Kaniel

๐Ÿ’ฐ Cost Tracker โ€” Plan vs Actual

Budget breakdown with real costs as they come in

Category Item Qty Plan (เธฟ) Actual (เธฟ) Delta Supplier Status
Panels LONGi Hi-MO X6 580W 56 280,000 โ€” โ€” RFQ sent Awaiting
Unit price estimate: เธฟ5,000/panel
Inverters Huawei SUN2000-11KTL-M5 2 120,000 โ€” โ€” RFQ sent Awaiting
Unit price estimate: เธฟ60,000/unit
Battery (Option C) Huawei LUNA2000-15-S0 2 550,000 โ€” โ€” RFQ sent Awaiting
Mounting No-drill clamps + rails 56 sets 56,000 โ€” โ€” RFQ sent Awaiting
Cables & BOS DC/AC cables, SPD, RCD, MCB, earthing 2 sets 40,000 โ€” โ€” RFQ sent Awaiting
Logistics Shipping to Surat Thani + ferry to KP 1 25,000 โ€” โ€” TBD Awaiting
Labor Installation team (Bustan Energy) 10 days 80,000 โ€” โ€” TM Dev Planned
Engineering Structural letter + PEA application 1 15,000 โ€” โ€” Rock Eng. Planned
TOTAL (EPC โ€” without battery) 616,000 โ€” โ€”
SALE PRICE (EPC) 1,056,250
GROSS MARGIN 440,250 (42%)